Projects
COMPLETED PROJECTS /2011-2016/
Rostov NPP Unit No.3
Design, manufacture and delivery of 1100 MW turbine and titanium condenser.
Delivery time: 2011.
Kalinin NPP: Unit No.1
Design, manufacture and delivery of condenser with stainless steel pipes for К-1000-60/50 turbine.
Delivery time: 2012.
Kalinin NPP: Unit No.2
Design, manufacture and delivery of modular condenser with stainless steel cooling pipes for К-1000-60/1500 turbine plant.
Delivery time: 2014.
Kalinin NPP: Unit No.3
Delivery of pipe systems for KP-1650 condensers of OK 12-A turbine.
Delivery time: 2014.
Balakovo NPP: Units No.2, No.3 and No.4
Design, manufacture and delivery of pipe systems with titanium cooling pipes and bimetallic tube plates for modular condensers of K-1000-60/1500-2 turbine plant.
Delivery time:
Unit No.4 – delivery ahead of schedule in 2014.
Unit No.2 – delivery ahead of schedule in 2015.
Unit No.3 – the first half of 2016.
Furthermore, components for modernization of К-1000-60/1500-2 turbine of Balakovo NPP, Units Nos.1-4, have been delivered.
Delivery time: 2014.
Novovoronezh NPP: UnitNo.5
Design, manufacture and delivery of pipe systems for modular condenser with stainless steel pipes for two K-500-60/1500 turbine plants.
Delivery time:
The first phase – 2014.
The second phase –in2015, ahead of schedule.
Rostov NPP: Unit No.4
Design, manufacture and packaged delivery of 1100 MW steam turbine with titanium condenser
Furthermore, control and protection systems, steam distribution units, oil supply systems and other auxiliary equipment have been delivered.
Delivery time: from 2013 to 2015.