“KomplekEnergo” takes part in delivery of equipment for Kursk NPP-2 being under construction (Units No.1 and No.2)* and it has large portfolio of orders till 2021.
Projects
It is planned to deliver the following:
2019-2020. COOLING PUMPS
Type of equipment: vertical diagonal-flow spiral pumps for main cooling water system; 4 units.
Delivery time:
• Unit No. 1 – November 2019
• Unit No. 2 – December 2020
Manufacturer: Sigma DIZ spol. s r.o. (The Czech Republic).
2019-2020. EVAPORATION PLANTS
The evaporation plants are made of corrosion-resistant steel and special alloys; they are meant for boron-containing water heat carrier processing system.
Delivery time:
• Unit No. 1 – August 2019
• Unit No. 2 – August 2020.
Manufacturer: ZAVKOM JSC (Tambov).
2019-2021. DECONTAMINATION FLUID HEATERS
Number: 6 pieces.
Delivery time:
• Unit No. 1 – October 2019
• Unit No. 2 – October 2021
2020-2021. VERTICAL CENTRIFUGAL-TYPE PUMPS
Type of equipment: vertical centrifugal spiral pumps, in number of 8 pieces.
Delivery time:
• Unit No. 1 – February 2020
• Unit No. 2 – March 2021
Manufacturer: Sigma DIZ spol. s r.o. (The Czech Republic).
* For reference:
The purpose of construction of Kursk NPP-2 is to substitute Unit No.1 and Unit No.2 of Kursk NPP on completion of their operating life. The first power unit of Kursk NPP-2 shall be commissioned by or before 2021, and the second one – in 2023.
(Source: www.rosenergoatom.ru)