Supply of 5 pipe systems PN-1200 was carried out within the following time limits:

- 2 tube systems PN-1200 were supplied in April 2017 – with four months ahead of schedule.
- 2 tube systems PN-1200 were supplied in December 2016;
-1 tube system PN-1200 was supplied in February 2017;

Heat-exchange equipment manufacturer was VITKOVICE Power Engineering a.s. (The Czech Republic).

In cooperation with VITKOVICE Power Engineering a.s., “KomplektEnergo” carries out modernization of heat exchange and mechanical equipment, i.e. low and high pressure heaters – (LPH and HPH) for Russian NPPs.

Photos

Back
Partners READ MORE
  • Taprogge GmbH (Германия)
  • Sigma DIZ spol. s r.o.
  • Elpanneteknik (Швеция)
  • ОАО «ОКБМ им. Африкантова»
  • ОАО «НПО ЦКТИ им. И.И. Ползунова»
  • ОАО «ВНИИАМ»
  • ФГУП ВО «Безопасность»:
  • ОАО «Концерн Росэнергоатом»
  • ОАО «Атомэнергоремонт»
  • ООО «Битруб Интернэшнл»
  • ГНЦ РФ ОАО НПО «ЦНИИТМАШ»
  • ОАО «НПО «ЭЛСИБ»
  • ОАО «Силовые машины»
  • ООО «ОМЗ Спецсталь»
  • ОАО «АКМЭ-инжиринг»
  • ЗАО «Атомстройэкспорт» (ЗАО АСЭ)
  • ОАО «Головной институт «ВНИПИЭТ»
  • ОАО «Атомэнергопроект»
  • TÜV SÜD Industrie Service (Германия)
  • Balcke-Dürr GmbH (Германия)